A Week-by-Week Breakdown of the Bathroom Renovation Process

What to Expect During Your Bathroom Renovation

A full bathroom renovation typically takes around 4 weeks, with each stage carefully planned to ensure a smooth transformation. Understanding the timeline helps you prepare for key milestones and any temporary disruptions. Here’s what to expect week by week.


Week 1: Demolition & Preparation

The first week is all about removing the old and preparing for the new.

🔨 What happens?
✔ Removal of old tiles, vanities, showers, toilets, and fittings
✔ Checking for hidden issues (e.g., water damage, structural concerns)
✔ Preparing floors and walls for waterproofing
✔ Setting up plumbing and electrical rough-ins

🚧 What to expect?
✔ Noise and dust—this is the loudest part of the process
✔ Your bathroom will be completely out of use
✔ If any unexpected issues arise, they’ll be addressed before moving forward

Tip: Have a temporary bathroom setup ready before demolition starts!


Week 2: Plumbing, Electrical & Waterproofing

With demolition done, new systems are installed and waterproofing begins.

🚰 What happens?
✔ Plumbing and drainage adjustments for new fixtures
✔ Electrical wiring for lights, power points, and exhaust fans
✔ Waterproofing application (walls, floors, and shower areas)

🚧 What to expect?
✔ Waterproofing requires drying time (typically 24-48 hours)
✔ Once sealed, the space will be ready for tiling

Tip: Ensure ventilation is maintained to help waterproofing dry properly.


Week 3: Tiling & Feature Installation

Tiling is a crucial step that sets the aesthetic of your new bathroom.

🛁 What happens?
✔ Floor and wall tiles are installed (including feature walls if planned)
✔ Shower niche tiling and grouting
✔ Sealing of all joints and edges

🚧 What to expect?
✔ Some noise from tile cutting and installation
✔ The room will start looking like a finished space
✔ Tiling and grouting take several days, with drying time needed

Tip: Large-format tiles create a seamless look, while small tiles add texture to feature areas.


Week 4: Fixtures, Fittings & Final Touches

The final week is about bringing everything together for a fully functional bathroom.

🔩 What happens?
✔ Installation of vanities, tapware, toilets, and showers
✔ Mirrors, towel rails, and lighting fitted
✔ Final plumbing and electrical connections
✔ Deep cleaning and final quality checks

🚧 What to expect?
✔ Your bathroom will be almost complete!
✔ A final walkthrough with your renovation team will ensure everything meets your expectations
✔ You’ll receive aftercare tips for maintaining your new space

Tip: If you’re leaving a Google review, you’ll receive a small thank-you gift!


Final Thoughts: A Smooth, Stress-Free Renovation

A structured renovation timeline ensures everything runs efficiently, with minimal delays. By understanding each stage, you’ll know what to expect and how to prepare.

At Custom Bathroom Creations, we prioritise on-time completion, clear communication, and high-quality finishes—ensuring a hassle-free renovation experience.

Ready to start your bathroom renovation? Contact us today to book a consultation!